Deck permits in Skokie, IL

Skokie says most construction or home improvement projects need a permit.

Is a permit required?

Skokie says most construction or home improvement projects need a permit.

"Most construction or home improvement projects in Skokie require a permit."

Source: skokie.org

Garages, fences, patios, decks and sheds are on Skokie's list of work that needs a permit.

"Garages, fences, patios, decks, sheds"

Source: skokie.org

What to bring

Deck applications must include a clear, legible plat of survey that the applicant confirms shows all improvements on site.

"The following permit types must submit a clear and legible plat of survey, with the applicant confirming that the survey is accurate and shows all improvements currently on site: Decks"

Source: skokie.org

Submit the original digital file of the plat; scans and photos are not accepted.

"Please submit the original digital file of your plat of survey. The Village will not accept scans or photographs of plats."

Source: skokie.org

Both the homeowner and the contractor must sign the permit forms.

"Both the homeowner and contractor must sign forms."

Source: skokie.org

How to apply

Decks go through the Building Permit track, which is for larger projects that need plan review.

"Decks, fences, or garages"

Source: skokie.org

All contractors must be licensed and bonded.

"All contractors must be licensed and bonded."

Source: skokie.org

Building & Inspection Services will say whether a project needs a permit.

"Contact us! We’ll help you figure out if your project needs a permit."

Source: skokie.org

Footings and frost depth

Skokie's amended residential code sets the frost line depth at 42 inches.

"Frost Line Depth ..... |42 inches |"

Source: library.municode.com

Inspections

Inspection requirements for the job are listed on the permit placard issued with the permit.

"Inspection requirements are listed on your permit placard"

Source: skokie.org

Final inspection requests must be submitted in writing.

"Final inspection requests must be submitted in writing"

Source: skokie.org

Other rules

The village amended the model code to delete several permit exemptions (building items 1, 2, 3, 4, 5 and 10 of Section R105.2).

"R105.2 Work exempt from permit. Delete Building items 1, 2, 3, 4, 5 and 10"

Source: library.municode.com

Before anyone digs

Illinois law requires a call to JULIE, the state's one-call system, before digging deck footings. Call 811 or (800) 892-0123, or file online, at least 3 days before work starts. The call is free, and the locate is good for 25 days. On a hired job, the company doing the digging makes the call. More on Illinois deck rules

We are not the City of Skokie. Rules change, and some neighborhoods and HOAs have their own. Confirm with the city before you build. Spotted something out of date? Tell us.